FICTIONAL DEMO WORKBACK — revised v2 Outcome at T0: demonstrate ONE agreed workflow with prepared sample data after rehearsal. The second workflow is excluded; this is not a production-readiness claim. Owner: one builder. B and C each require full attention; do not overlap them. Time convention: T0 = demo start. T-4 to T-3 is one full WORKING day. Use a declared working calendar; map to dates only after confirming hours, holidays, availability, timezone and exact cutoff. Available interval: T-10 to T0. A: agree narrower scope | 1 day | T-10 to T-9 | no predecessor Done: one workflow agreed; second workflow explicitly excluded. B: build narrower prototype | 3 days | T-9 to T-6 | needs A Done: agreed path runs. Three-day estimate depends on accepted scope reduction. C: prepare sample data | 2 days | T-6 to T-4 | needs A; follows B for owner capacity Done: data matches the agreed path. D: assemble demo | 1 day | T-4 to T-3 | needs B AND C Done: prototype and data work together. E: rehearse | 2 days | T-3 to T-1 | needs D Done: complete run; remaining issues resolved or explicitly disclosed. BUFFER: 1 day | T-1 to T0 | record use and remaining allowance. Total: 1 + 3 + 2 + 1 + 2 + 1 = 10 working days. Original scope needed 11 with one owner; nine days assumed independent B/C capacity. If the three-day prototype estimate is not credible: reconfirm scope, a qualified second owner, or a later demo date. Do not silently overlap full-attention tasks or delete rehearsal/buffer. Still to fill for real use: authoritative event reference, actual dates, timezone/cutoff, calendar exceptions and scope approval reference. Change rule: revise detailed schedule first; then update any day countdown. Readiness follows handoff evidence, not the countdown value.